470 infra projects show cost overruns worth Rs 4.38 L cr

| | New Delhi
  • 0

470 infra projects show cost overruns worth Rs 4.38 L cr

Monday, 31 May 2021 | PTI | New Delhi

As many as 470 infrastructure projects, each worth Rs150 crore or more, have been hit by cost overruns totalling more than Rs4.38 lakh crore, according to a report.

 The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs150 crore and above. Of the 1,737 such projects, 470 reported cost overruns and 525 were delayed.

“Total original cost of implementation of the 1,737 projects was Rs22,33,409.53 crore and their anticipated completion cost is likely to be 26,71,440.77 crore, which reflects overall cost overruns of 4,38,031.24 crore (19.61 per cent of original cost), “ the ministry’s latest report for April 2021 said.

 According to the report, the expenditure incurred on these projects till April 2021 is Rs13,16,032.62 crore, which is 49.26 per cent of the anticipated cost of the projects.

 However, the report said that the number of delayed projects decreases to 375 if the delay is calculated on the basis of the latest schedule of completion.

Further, for 988 projects neither the year of commissioning nor the tentative gestation period has been reported.  Out of 525 delayed projects, 106  projects have an overall delay in the range of 1-12 months, 123 projects (13-24 months), 179 projects (25-60 months) and 117  projects (61 months and above).

 The average time overrun in these 525 delayed projects is 45.63 months. 

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

The report also cited ‘state-wise lockdown due to COVID-19’ as a reason for the delay in implementation of these projects.   It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported, it added.  

Sunday Edition

Grand celebration of cinema

17 November 2024 | Abhi Singhal | Agenda

Savouring Kerala’s Rich Flavours

17 November 2024 | Abhi Singhal | Agenda

The Vibrant Flavours OF K0REA

17 November 2024 | Team Agenda | Agenda

A Meal Worth Revisiting

17 November 2024 | Pawan Soni | Agenda

A Spiritual Getaway

17 November 2024 | Santanu Ganguly | Agenda

Exploring Daman A Coastal Escape with Cultural Riches

17 November 2024 | Neeta Lal | Agenda