Bhopal Municipal Corporation (BMC) Commissioner K.V.S.Chaudhary visited the Pradhan Mantri Awas Yojana and inspected the prevailing works of Malikhedi project under and in relation to the existing and proposed works, from the officers discussed in detail.
Commissioner Chaudhary Malikhedi visited the Pradhan Mantri Awas Yojana at Malikhedi on Tuesday. During the visit he was instructed to maintain the quality and continue to maintain pace of the work to complete the work on time.
The work of the sewer line, water supply line, drainage and electricity connection were inspected by the Commissioner and instructed for completion of other works including pending works. Demarcation and marking etc and preparation and submission of plans was instructed.
During the inspection, Additional Commissioner Sandeep Kerketta, Superintending Engineer RK Saxena and other officers of the corporation were present. Chaudhary instructed to complete construction of internal works including sewer line, drainage.
The work of Electric poles and transformer installation work and other works have to be completed within the time limit.
He instructed them to prepare the base in advance, so that the Cement Concrete road (CC) works could be completed before the rainy season.
Information of EWS construction works of slum and non slum blocks was discussed by the commissioner and instructed to complete within the prescribed time limit.