The Municipal Corporation of Delhi has cleared a special provision for the Delhi Jal Board to dig up and restore roads while laying and replacing nearly 1,000 km of pipelines under a World Bank-assisted project.
The MCD’s Standing Committee on Thursday approved a special provision allowing the DJB to undertake road-cutting and restoration work under the ‘dig and restore’ policy on a case-to-case basis.
The move, which could benefit residents across the national capital with improved water supply, follows a request by the water utility citing the project’s strategic importance and the need to expedite its execution, they said.
Spread across around 96 square kilometres, covering nearly 6.5 per cent of the national capital’s geographical area, the Delhi Water Supply Improvement Project encompasses areas under Timarpur, Model Town, Sadar Bazaar, Chandni Chowk, Matia Mahal, Ballimaran, Karol Bagh, Patel Nagar, Rajinder Nagar, Jangpura and RK Puram, among other constituencies.
“Under the ‘dig and restore’ provision, the agency carrying out excavation is responsible for restoring the road through an authorised contractor. This differs from the ‘dig and deposit’ policy, under which the agency deposits the estimated restoration charges with the road-owning authority, which subsequently undertakes the repair work,” a senior official said.
After concerns were raised over the quality of restoration carried out by agencies digging up roads for laying pipelines, cables and other utilities, the MCD had discontinued the ‘dig and restore’ provision in 2024, retaining only the ‘dig and deposit’ policy, under which the road-owning agency takes responsibility for restoration.
Another official said both arrangements had earlier coexisted, but the corporation had to discontinue the former following repeated complaints about poor-quality restoration.
“Agencies would dig up roads for their utility work and restore them with substandard materials, affecting roads’ condition and durability,” the official said, adding that this prompted the civic body to stop the ‘dig and restore’ arrangement in 2024.
The special permission for the DJB project will allow the water utility to undertake restoration itself, subject to safeguards, inspections and quality certification.
Officials said that the Jal Board will have to deposit a refundable security amount equivalent to 10 per cent of the estimated road restoration charges or Rs 2 lakh, whichever is higher, before starting excavation.
The amount will be refunded after satisfactory restoration and submission of the requisite completion certificates, subject to recovery of any outstanding dues or damages, they added.
The permission will be processed through an online system, with joint site inspections by the DJB and the concerned road-owning agency. A third-party quality assurance agency will also have to inspect and certify the restoration work.
“The DJB will have to ensure that restoration begins within 48 hours of completion of the utility work and is finished within the stipulated period. The agency will also be required to comply with National Green Tribunal guidelines and road safety norms. Periodic inspections will be carried out to assess the quality of restoration,” the official said.