Expedite clean Yamuna projects: Kejriwal

Published on: 

Delhi Chief Minister Arvind Kejriwal on Thursday reviewed the major projects pertaining to the cleaning of the Yamuna River and stressed upon completion of projects before the scheduled timeline.

Kejriwal directed the officials to ensure that no untreated wastewater flows into the river noting that water of four major drains are falling into the river. The DJB officials represented a detailed plan to clean four major drains such as Najafgarh, supplementary, Shahdara, and Barapullah in the meeting.

The Chief Minister expressed concerns and unhappiness over the delays in the timelines of each Sewage Treatment Plants (STP) project. He instructed the officials to have a detailed plan ready by next week, wherein every project is scrutinised as per the revised timelines.

While directing the officials to expedite the Yamuna cleaning project, Kejriwal said, "The Clean Yamuna project is one of the most ambitious projects of the Delhi Government. We must ensure that there is no laxity at any phase of the project. We should work towards expediting the Yamuna cleaning process; every sub-project should be completed within the stipulated time frame."

The DJB officials apprised Kejriwal that various low-cost technological interventions are being done to expedite the work before scheduled timelines.

“Out of the four drains, the work on interception of two major drains i.e. supplementary and Shahdara is almost complete. The untreated water from the supplementary drain will be completely tapped and treated by December 2021. The untreated water from the Shahdara drain will be completely tapped in the next few months. The remaining two major drains such as Najafgarh and Barapulla will be completed within the stipulated deadline,” they said.

Kejriwal also reviewed the flagship project of septic tank cleaning in unauthorised colonies of Delhi. The project is expected to be completed within the next few months.

 The DJB officials also apprised the chief minister that various low-cost technological interventions are being done to expedite the work before scheduled timelines which include in situ

treatment of wastewater, tapping of complete drains and conveyance to STPs for treatment, installation of advanced filters, incineration for sludge volume reduction, quality improvement of effluent parameters of existing STPs, capacity augmentation of STPs through aeration system.