Raipur

CSPDCl installs 45-km HT line

Staff Reporter

The Chhattisgarh State Power Distribution Company ltd (CSPDCl) has so far established a total of 56 new ‘high tension power sub stations’ in the State.

With this, the total installed capacity of the ‘HT Sub Stations’ has reached 11,826 MVA, according to a CSPDCl Press release issued here on Tuesday. The latest HT line established has a length of 45.2 km extending from Raipur’s 400 KV Sub Station at Raita village to Bhilai-based Sub Station at Khendamara.

CSPDCl managing director Vijay Singh stated that 31 new power distribution sub stations are currently under development costing  rs 1350.92 crore in the State. The total length of the circuit line in the State now stands as 9832 km.