Raipur

Chhattisgarh electrifies 686 out of 1,080 villages so far

Staff Reporter

A total of 686 villages out of 1080 have been electrified in Chhattisgarh so far, Government officials have revealed here on Saturday.

Nationally, 13,002 villages have been electrified till date under Deen Dayal Upadhyaya Gram Jyoti Yojna (DDUGJY). Out of remaining 5450 un-electrified villages, 835 villages are uninhabited. All the remaining 4615 un-electrified villages are to targetted to be electrified by  May 1, 2018.

In view of the Prime Minister, Narendra Modi’s address to the nation on Independence Day, the Central government has decided to electrify remaining 18,452 un-electrified villages within 1000 days ie by May 1, 2018. 

The project has been taken on mission mode and strategy for electrification consists of squeezing the implementation schedule to 12 months and also dividing village electrification process in 12 Stage milestones with defined timelines for monitoring.

In order to expedite the progress further, a close monitoring is being done through Gram Vidyut Abhiyanta (GVA) and various actions are also being taken on regular basis like reviewing the progress on monthly basis during the RPM meeting, sharing of list of villages which are at the stage of under energization with the state DISCOM, identifying the villages where milestone progress are delayed.

The Chhattisgarh Government has targetted to spend Rs 5,036 crore for augmenting rural electrification and energy distribution system, officials informed.

Notably, the power supply distribution augmentation system project would be funded by Central government grant, equity contribution from State and loan from financial institutions.

The State-owned Chhattisgarh State Power Distribution Company ltd (CSPDCl) which is implementing the project has sought additional funding support from the Central Government for achieving 100 per cent electrification of villages in Bastar region by FY 2018.

The special scheme would require additional finding support of Rs 665 crores of additional investment from the work carried out under Deendayal Upadhyay Gram Jyoti Yojana , officials informed.

Notably, Chief Minister Raman Singh  had recently reviewed works of Energy Department and issued directives to complete construction of 34 key power sub-stations in various districts of state including tribal stronghold Bastar and Surguja divisions within 18 months.

The construction cost of these 34 power sub-stations is estimated to be Rs 2100 crore.

The Chief Minister said in the meeting that keeping in view the demands and requests for electricity supply received from villagers during state-wide lok Suraaj Abhiyan, these power substations should be constructed within the time-limit on priority basis, so that quality electricity supply could be ensured in far-off rural regions.

In the meeting officials informed that two power substation of 400/220KV will be constructed in Jagdalpur and Dhamtari, eight power substations of 220/132 KV will be constructed in Rajim, Borjhara (Gariaband), Parsada, Kawardha, Dharsiva, Narayanpur, Jagdalpur and Bilaspur. likewise, 24 power substations of 132/33 KV will be constructed in Koni, Ravanbhata, Batauli, Kondatarai, Sukma, Charama, lormi, Dabra, Bakhara, Vandanapuling, Shivrinarayan, Wadrafnagar, Kansabel, Bijapur, Pakhanjur, Nagri, Indagaon, Mohla, Rajpur, Dornapal, Takhatpur, Basna, Berla, and Renki (Korba).