The Energy Management Department of Bhilai Steel Plant has safely and successfully commissioned about 650 RM (running metre) of diametre 1400 mm main Coke oven gas line for Blast Furnace-8 recently.
For connecting new header with existing gas network, shutdown of URM coke oven gas line was taken for three shifts, a BSP press release informed.
After purging and ensuring normal sample the new gas line was safely connected and successfully commissioned. With the commissioning of new coke oven gas line, stoves of Blast Furnace-8 can now consume gas for heating purpose.
The gas line project was carried out under the leadership of Navin Kumar DGM I/c (EMD) and under the guidance of P.K. SinghDGM (Gas Safety &Opr) EMD.
The commissioning of gas line was successfully done by team EMD consisting of S.K. Dashore, DGM (gas Saety), S. Ramani AGM (Gas Safety), Y.Y. Konnure AGM (O) EMD, S.R. DhruwAsttMgr (Gas Safety), U.K. TarafdarAsttMgr (O) and UdaiPande, T.N. Jaiswal, Akhil Ahmed from Gas Safety.
Necessary support and coordination from Projects Dept was extended by A. Guha GM (Project), Biplab Dey DGM, Ashok Kumar, DGM, RishabhYaduraj, DyMgr and M/S Tata Projects. All help was provided by Bhilai Fire Services and Safety Department to execute the job with utmost safety.