The Asian Development Bank (ADB) had been helping the Chhattisgarh Government upgrade about 916 kilometres of roads in the State. The works include development of new road sections, two laning works, constructing and strengthening culverts and bridges, the officials stated.
Notably, new stretches of rural roads are rapidly coming up in Chhattisgarh with massive funding support from ADB, officials said. The ADB has provided lending support to Chhattisgarh for projects undertaken under Prime Minister’s Gram Sadak Yojana (PMGSY).
The international funding agency had been helping to either construct or upgrade 31,000 kms of rural roads in the States of Chhattisgarh, Madhya Pradsh, Odisha, West Bengal and Assam nationally, officials stated.
Notably, the Chhattisgarh Government has already started taking steps to even settle the forest land disputes under the Forest Protection Act 1980 as early as possible for accelerating the process of laying of roads under the Pradhan Mantri Gram Sadak Yojana (PMGSY) (Prime Minister’s Rural Roads Project), officials mentioned.
A time-bound action plan has been chalked out for various departments to settle the issues relating to forest land expeditiously, officials stated. Chief Secretary Vivek Dhand in a circular issued last year had directed that all the road works should be completed in a time-bound manner.
The Chief Secretary said that the land area should be inspected by the Forest Department officer on the next day itself. The District Collector should be informed if there is any delay. The concerned Collector should settle the issue in within 10 days. The time-frame has been fixed as per the hectares of forest land.
The officers of Panchayat and Rural Development Department in a State-level Standing Committee of Panchayat and Rural Development Department chaired by the Chief Secretary in December last year had taken stock of the status of roads and structures being constructed under PMGSY.
It was informed in the meeting that 5124 permanent roads have been constructed in Phase 1 to 8 of the scheme. The total length of these roads is 22750 km. These include roads constructed in Phase 1 to 8 of the scheme besides roads constructed in different phases of Rural Road Connectivity Programme of the Asian Development Bank.
The construction of these roads has facilitated people of 7610 rural settlements for commuting in these all weather roads, it was informed.
In the meeting it was also informed that construction of 337 roads was completed at a cost of Rs 715 crore under PMGSY in the financial year 2013-14. The length of these roads is 1292 km and their construction has linked 969 settlements.
As many as 37 roads have been sanctioned under the advance technology of PMGSY. Among these, construction of four roads has been completed while construction of 10 roads is under progress. The process of tender agreement is completed for five roads while tenders for 18 roads are under process.
In the meeting, the officers informed that proposals for construction of 294 roads worth Rs 1023.51 crore and construction of 103 bridges worth Rs 1318 crore was been sent to the Central government for financial year 2014-15.
The Central Government has approved a revised cost of Rs 3045 crore under its Road Requirement Plan (RRP) for improvement of road connectivity in left Wing Extremism (lWE) affected areas of Chhattisgarh.
Overall, the Centre has approved a Road Requirement Plan (RRP) for improvement of road connectivity in left Wing Extremism (lWE) affected areas of a total of 34 Districts in 8 States covering 5477 km length (1126 km NHs & 4351 km State Roads.
In Chhattisgarh, the fund had been approved for improvement of road connectivity in left Wing Extremism (lWE) affected areas measuring 2019 kms.
As per details of Physical Progress achieved as on March 1, 2015 under RRP the length of road completed between 2010-11 to 2014-15 in the insurgency infested areas in Chhattisgarh upto February 28,2015 is 868 kms.
As per the State-wise details of fund allocated and expenditure incurred under lWE scheme, Chhattisgarh an expenditure of Rs 190 crore was made from 2010-11 to 2014-15 upto February 28, 2015.