Noida Sec 62 metro link to start in Aug

Abhishek Byahut

As the construction work of metro projects between Noida to Greater Noida, and Botanical Garden to Kalindi Kunj continue in full swing, the Noida Authority on Friday said that it has decided to start the construction work of 6.675-kilometer-long metro extension line between Noida Sector 32 and Sector 62 from August first week.

An authority official said that Delhi Metro Rail Corporation (DMRC) has floated its tender and its technical bid has been opened on May 22. Nine companies have showed their expression of interest in this project. The financial bid will be expected to open on July 20 to select any one company out of nine that will start the construction work on this project.

Additional Chief Executive Officer of Noida Authority Pramod Kumar Agrawal said, “Nine companies have showed their expression of interest in this project that will be finalized in financial bid schedule on 20 July. The work on this project is to start from August.”

Ajay Sharma, Chief Project Manager (CPM), DMRC said that Noida Authority is working on shifting and relocation of plants and high-tension wires passing from this route. DMRC has floated a tender and the contract should be finalized in August, after which the work is expected to start.