During the lockdown, works of Noapara- Bimanbander Metro Extension Project have been going on smoothly. Excavation of tunnel of this Metro project has been started. Base concrete of Grade M-20 for bottom slab of the tunnel has been completed recently. Casting work of the top slab is in progress.
Two numbers of PSC Box Girders of 20-22 m span have been safely unloaded in this period with the help of a main crane of 600 MT capacity.
Casting of five numbers of PSC 1 girder of 20-22 m span has been completed during the lockdown period. Social distancing, sanitization, covering faces with masks.