After successfully linking the transmission line from Assam to Agra, which will be commissioned on August 30 this year, State-owned Navratna company Power Grid Corporation of India limited (PGCIl) is expecting to complete the 1350km-stretch Champa-Kurukshetra link by July next year.
“As we have successfully completed this Assam-Agra line as per our scheduled plan, we are hopeful that our 1350km-stretch Champa-Kurukshetra link with capacity of 800KV high voltage direct current (HVDC) transmission line would be completed in a year’s time, most probably by end of July 2016,” a PGCIl official told The Pioneer at the sideline of its grid terminal visit here.
The link from Champa in Chhattisgarh to Kurukshetra in Haryana with 6,000MW capacities each will help in transmission, thereby stabilising the grid failure in the future. “The very nature of control power flow of the HVDC interconnection provides additional flexibility in the grid operation, thereby improving various grid parameters in the country,” the official added.
Besides, the Corporation has also a plan to execute Raigarh-Pugalur-Trichur link with capacity of 800KV and 6,000MW HDVC in the near future. The project is now under tendering stage.
As far as the Champa-Kurukshetra link is concerned, French energy solution and transport company Alstom has been given the contract for building a transmission link between Haryana and Chhattisgarh.
This new 3,000MW transmission link will run parallel to the first HVDC transmission link awarded to Alstom in 2012, increasing the total transmission capacity of the system to 6,000MW. “The link will transfer clean, bulk power efficiently from the Chhattisgarh region to the load centre in the northern region of the country,” the official said, adding that all equipment will be manufactured by Alstom’s facilities in India, United Kingdom, France and Italy.
The plan of the project came to floor in mid 2013, he said, but execution started in 2014 due to land issues and other teething problems. “land issues took much of its time, over six months due to the delay of getting permission from the respective State Governments in this matter. After getting the go-ahead notice from these Governments, we started executing the project. Now, it is in full pace and we hope it would be completed as planned,” he said.
Meanwhile, the company announced that the 1,730-km-long 800-KV HVDC transmission line would start commissioning on August 30. “The total cost involved to erect transmission line from Bishwanath Chariali in Assam to Agra is around Rs12,000 crore - Rs6,000 crore for 3 terminals and another Rs6,000 crore for transmission will help transmit 6,000 MW of electricity,” the official said.
“The high capacity HVDC corridor shall integrate the north-eastern regions with other regions of the country to facilitate smooth and reliable power transfer giving rise to a stable National Grid. Any transmission system planned to interconnect North Eastern region with rest of the Indian grid shall have to be of high capacity as it has to pass through the Chicken neck area in Siliguri district of West Bengal in Eastern region having an acute constraints in the availability of right of way,” he added.
A consortium of BHEl and ABB was given the order for the supply of equipment for the transmission line. “The planning of the project was started in 2007 and its execution took place in 2012,” he said.
The link will act as a highway from North-Eastern region to rest of the country and will play a significant role in the hydro potential in the north-eastern parts of the country as well as lead to attain socio-economic development of India as a whole and the region in particular.