Bhubaneswar

Posco spells out timeline for project execution

PNS

Submitting a statement of facts to the State Government, Posco has spelt out the schedule it is to follow for starting of production from its proposed steel plant and the iron ore mines it is to be allotted.

 The South Korean company has stated that it requires three years for completion of prospecting, including obtaining of forest clearance. Thereafter, it would require four years for commencement of the first phase of mining operation which includes three years for processing mining lease including forest and environment clearance and another one year for first phase mines development.

 The mines can be fully operationaliaed by another three years thereafter, said the statement.

 After obtaining the National Green Tribunal’s (NGT) clearance and revalidation of environment clearance, 18 months would be required for land filling, which would be followed by construction activities of the plant, requiring another two years. After that, one more year is required for commissioning and testing of the plant.

 During the gap of commissioning and production from mines, the company would arrange iron ore on its own, said the statement.    Optimistic about progress of Posco’s `52,000-crore project, the State Government has said it would sign a fresh tripartite agreement with the company as the validity of the original MoU lapsed three years ago.

Steel and Mines Minister Rajani Kanta Singh said the fresh agreement would be signed based on a guideline given by the Centre.He, however, said the project work could continue even without having any agreement with the company.