BMC Commissioner order to expedite rail track works

Staff Reporter

The upper part of the railway tracks and slab towards Hoshangabad Road of the railway overbridge (ROB) should be completed by the end of the month of February, instructed BMC Commissioner Tejaswi S Naik during his visit on Thursday.

The work of girder placement should be done by January and the upper part over railway tracks and slab casting towards Hoshangabad road should be completed by February instructed Naik. 

In the second span a 120 ton girder was placed using two cranes having capacity of 220 metric ton and 120 metric ton while the continuous work is under process to place remaining 21 girders.  

The slab casting is scheduled to be completed by March 2016 and during the inspection he instructed to complete the slab casting of ROB within the stipulated time. The instructions were given by Naik during his visit on Thursday.

Assistant City Engineer OP Bhardwaj, CEO of construction company Suhash Eklahare, officials of BMC and other officials were present during the inspection.

Meanwhile Hotel Jehanuma Palace has been issued notice for unauthorised hoardings and advertisement at city squares by Bhopal Municipal Corporation; orders have been issued in violation of orders of High Court and violating Bhopal Municipal Corporation (Advertisement) law and Property Distortion Act and have instructed to reply within 24 hours.

BMC has issued notice to Hotel Jehanuma Palace after the unauthorised advertisements by the hotel were found at Polytechnic Square, 5 no. stop area, link road no. 2 area.

The advertisements are not only violating the laws but also disturbing the beauty of the city, the notice said, stating that in case if the hotel management fails to reply on the notice action would be taken against the hotel.