The judicial rescue of the stalled Amrapali housing projects stands as one of the brilliant historic structural remedies executed by the Supreme Court of India. By replacing a defaulted promoter with a Court Receiver mechanism and deploying state-owned National Buildings Construction Corporation (NBCC) as the project execution agency, the Apex Court provided hope to more than thirty-five thousand stranded families when all other institutions had either remained silent spectators or chosen inaction. Possession letters have been issued to 51 homebuyer families at the Leisure Valley Adarsh Awas Yojana project.
The handing over ceremony was held on 23rd October 2026 in the presence of the Court Receiver (CR) and Attorney-General Sri R Venkataramani and NBCC CMD Dr KP Mahadeva Swamy. The NBCC is in the process of completing all 24 projects in Phase I, and so far around 13,000 crores worth of work has been completed.
Under the direct supervision of the Supreme Court, the NBCC completed construction work across multiple phases and handed over physical keys to their apartments.
The buyers who had endured over a decade of financial distress-paying both monthly home loan EMIs and house rents-expressed relief at the culmination of their long wait. Mr R Venkatramani, soon after taking charge, did an unprecedentedly splendid job in mobilising financial and other resources in record time. However, at ground zero-particularly in complexes like Amrapali Centurian Park-the noble objectives of the Supreme Court are running into severe operational headwinds. A growing disconnect between administrative mechanisms, execution boundaries, and resident governance threatens to derail the benefits of this high-level intervention.
While NBCC's mandate remains strictly confined to completing baseline construction and physical key handovers, day-to-day estate management and operational civic facilities often fall into an administrative vacuum. The Office of the Court Receiver, designed to oversee high-level financial flows, regulatory approvals, and project completion, was never structured to function as a daily property management office. As a result, individual grievances submitted by home buyers frequently go unacknowledged.
Compounding this institutional bottleneck is the prevalence of unrecognised, "ad-hoc" Apartment Owners Associations (AOAs) who have been squabbling all the time due to inexperience and personal agendas. Lacking statutory standing under the UP-Apartment Act, these interim bodies often slide into localised politics, financial opacity, and internal factionalism, leaving residents without effective, accountable representation. Now, new challenges have surfaced across several delivered blocks, including seepage, incomplete common amenities, parking allotments, maintenance disputes, and transitional operational friction. As home buyers move into their units, post-handover operational and construction-related issues frequently arise. Below are urgently needed actionable recommendations to effectively address these challenges.
· A thorough snagging (a technical term used for inspecting the construction) audit is necessary before possession sign-off, for which NBCC and the Court Receiver need to hire an independent civil engineer or home inspection service to carry out a comprehensive "snagging list" audit (checking wall seepage, plumbing leaks, electrical wiring, tile hollows, and door/window sealing), as large numbers of these complaints are a regular feature. The auditor should submit a formal signed snagging report to the NBCC site office before signing final satisfaction notes or moving furniture in.
· The Office of the Court Receiver has explicitly stated that NBCC's primary role is project execution, while day-to-day maintenance transitions to resident bodies. But before this, the Court Receiver's office needed to direct NBCC to take steps for many unresolved issues. The Home buyers must escalate this to AOA, then to NBCC and then to the Court Receiver. It is not out of place to mention that NBCC had taken over the de facto as well as De jure responsibility of the builder.
· There should be no room for the Ad hoc A0A and the Court Receiver's office must ensure the formalisation of a registered, transparent Apartment Owners Association (AOA) under the UP-Apartment Act, 2010. There after the AOA should oversee the joint inspection and handover of common facilities (elevators, power backup, fire safety equipment, basements, and STP units) from the contractor.
· The maintenance agencies should be hired by the NBCC till full-time, regular AoA are constituted because the existing Ad hoc arrangements in Centurian Park Terrace Home have become a joke and a contest of musical chairs to grab power. The Court Receiver must take note of the totally mismanaged Terrace Home AoA due to the power game being played by rival groups. This AoA has become unmanageable due to large numbers of flats of different sizes. This AoA must be divided into two AoAs. One for A Block, which has more than 250 flats of higher areas and the other for B and F blocks. The entrance and Exit can be separated by NBCC. All attempts should also be made to finish the completed projects by ensuring registration with the sub-registrar office.
· A formal Handover Cell comprising representatives from the Court Receiver's Monitoring Committee, the NBCC Site Director, and the President/Secretary of the formally elected AOA must be operationalised. This task force would clearly demarcate NBCC's statutory defect-liability obligations while smoothly transitioning daily operations, security, and maintenance corpus management to the democratically elected AOA. An intervention that set a national precedent for protecting homebuyer rights cannot be allowed to stall in its final mile. Strengthening democratic resident representation, streamlining communication channels, and maintaining firm judicial monitoring will ensure that Amrapali Projects achieves both structural completion and sustainable, accountable governance.
· Last but not least, if systemic responsiveness issues persist, homebuyer groups should aggregate ground-level facts into a unified Interlocutory Application before the Supreme Court Bench oversight panel. Direct judicial intervention remains the ultimate tool to ensure that executive authorities and project administrators adhere strictly to the Court's original vision.
The writer is former Principal Secretary Government of Tripura and Chairman of Centre for Resource Management & Environment; Views presented are personal.