A 1800 mm ‘Coke Oven Gas line’ was safely and successfully commissioned by Energy Management Department of the Bhilai Steel Plant (BSP) here. Meticulous planning, site preparatory and detail job discussion with various agencies were required to commission the above gas line.
Full safety precautions were observed. Besides these, the network coke oven gas pressure of the plant was reduced to 300 mmwc to enable safe execution of gas job, a BSP press release stated.
De-blanking of live ‘Coke Oven Gas line’ and commissioning of new gas line to CDCP could be completed successfully with 100 per cent safety due to commendable dedication displayed by the collective, the press release stated.
The commissioning of gas line was accomplished under the leadership of Bipin Kumar GM (EMD) and guided by P.K. Singh DGM (Gas Safety) EMD, Naveen kumar DGM I/C (Opr) EMD and Safely executed by S.K. Dashore AGM (Gas Safety) EMD, S.
Ramani AGM (Gas Safety) EMD, R.S. Sharma Mgr (Opr) EMD, P.R. Thakur Astt Mgr (Gas Safety) EMD, S.R. Dhruw Astt Mgr (Gas Safety) EMD, D.S. Chauhan (DSO) EMD. Support was provided by Gas Safety (EMD), Fire Services, Project, SP-III, COCCD, CISF, Medical, SED & T&D, it stated.