Progress report on 'Bhagirathi Nal-Jal Scheme' sought

Published on: 

Municipal Commissioner D. Singh has directed the officers of Water Supply Department to present daily progress report of the work on water supply connections being provided under ‘Bhagirathi Nal-Jal Scheme.’

Singh reviewed the progress of the scheme in a meeting with the officers and contractors of the civic body’s Water Supply Department here. The Commissioner took information from the officers about pipeline extension work being undertaken under the 13th Finance Commission and directed them to complete the work in the given time frame.

He instructed the contractors to complete the remaining work of inter-connection in Ward number 1, 4, 5 and 6 within 15 days. Singh said that the pipeline leakage underneath the Railway tracks cannot be repaired since permission is yet to be received from the Railway administration.

He directed the Assistant Engineer Jainarayan Srivastava to send a letter to the Railway administration through Collector in this regard. For inter-connection works which need road cutting, Singh directed the Assistant Engineer to send a letter to the Public Works Department to get permission for road cutting.

Singh also directed the officers to prepare proposal for construction of water tank in Motipur and Pendri besides preparation of estimate for inter-connection of 27MlD and 10 MlD in Nalghar, Mohara.

He said that the remaining work of Mohara filtration plant should be completed soon. Deputy Engineer Atul Chopra, Yuvraj Komre, Tushar Shukla, Sanjeev sahu, Kiran Chauhan, and others were present in the meeting.