Power sub-station commissioned for Coke Oven Batteries at BSP

Published on: 

Under the seven million tonnes (MT) expansion and modernisation programme of Bhilai Steel Plant, the 11KV and 6.6KV power for Coke Oven Battery was commissioned, a statement of the plant informed here on Saturday.

M/s ABB India ltd constructed this substation under Pkg-71A with the supervision by Projects-Power Zone and active involvement of Power Systems Department.

S.K. Pradhan, former Executive Director (Projects) inaugurated ceremoniously this HT substation in presence of Project General Managers– S.K. Ghosh & Anirudh Guha, K.R. Paul Chaudhari, GM (MECON) and C.R.V. Sudarshan, AVP (ABB India ltd).

Senior officers of Power, Electrical Testing, IATRS & Coke Zone of Projects Organisation, COCCD, Power Systems Department, ETl & INCOS were also present on the occasion. Pradhan congratulated Projects, PSD & ABB collective for the timely completion of this substation which enabled Charging of Coke Oven Battery and commissioning of other associated facilities.        

Daily Pioneer
dailypioneer.com