Chief Minister Raman Singh informed the Chhattisgarh Assembly on Tuesday that both the units of 2x500 MW Marwa Thermal Power Station (TPS) at Tendubhata in Janjgir-Champa district are operational and have been producing on an average 800 to 880 MW of power.
In a written reply to Congress member Bhupesh Baghel, the Chief Minister informed that the power production was commenced from Unit -I and II at the Marwa thermal power station on March 31, 2016 and July 31, 2016 respectively.
The Marwa Power Plant had been allotted Gare Pelma Sector-III coal mine block in Raigarh district and the coal extraction contract had been offered to M/s Adani Enterprises ltd , Ahmedabad, on June 24, 2016, he said.
The open bidding for the Gare Pelma-III block was done by Chhattisgarh State Power Generation Company ltd (CSPGCl) through an international bidding process, Singh informed.