The work on the Fafadih-Telibandha-Atal Nagar (Naya Raipur) four-lane Expressway on narrow-gauge line land construction is in progress. Chhattisgarh Road Development Authority has sanctioned Rs 313 crore for the construction. Public works Department Minister Rajesh Munat has said that till date around Rs 275 crores has been spent on construction.
The total length of 12 kilometres route has four fly-over, the construction of which is in progress that are situated at Fafadih, Devendra Nagar, Pandri and Shankar Nagar. Additional to it elevated corridor is being constructed at Avanti Vihar and Telibandha.
The four-lane road and seven kilometres service road construction is also in progress. On it eight small bridge and 12 bridges are also being constructed where as three under bridge pass is also under construction. The three under bridge is at Pandir, Amlidih and Gudhiyari. The construction works is expected to be completed by this month end.