Uttarakhand Vidhan Sabha Speaker Govind Singh Kunjwal sounded angry on Monday at snail pace with which works of the power corporation is progressing at Gairsain where the next Assembly session is slated to begin on November 2. He instructed the officers concerned to complete the assigned work well before the time the next Assembly would sit.
During his visit to Gairsain, Kunjwal inspected the venue of the session, Polytechnic college building and instructed the working agency to complete all arrangements by October 15.
He also directed Public Works Department to ensure parking facilities for the upcoming session. He asked Garhwal Mandal Vikas Nigam to make arrangement for lunch to be served to the MlAs who would attend the session.
Kunjwal also inspected the rooms meant to be used by the MlAs to stay during the session in Bharadisain and asked the agency concerned to complete things by the deadline. The old and new pipe lines must be laid to ensure smooth supply of water to those who would attend the session, added Kunjwal while instructing Peyjal Nigam.
Kunjwal expressed anger over the sluggish pace with which the electricity department is doing its works. “They have not cared to comply with the instruction given to them to install the under- ground line from Dwarikhal to Bharadisain and also to install street lights,” he rued.
BSNl has been asked to make arrangement of Wi-fi, he said, adding that PWD has been instructed to construct helipad in Bharadisain and Saliyana.
Chamoli district magistrate Ashok Kumar, superintendent of police Sunil Kumar Meena, SDM Gairsain K.S.Negi and other officers of the different departments were present during the inspection.