Khandagiri flyover by July

Published on: 

The ongoing flyover construction work on National Highway-16 at the accident-prone Khandagiri Square here would be completed by July this year. About 70-per cent work has already been done, NHAI Odisha Chief General Manager Ram Prasad Panda has informed. The flyover, which was to be completed by September 2020, is delayed by 10 months due to coronavirus pandemic. The six-lane, 2.230 km-flyover project began with an estimated cost of Rs 115 crore in June 2019.  