Essar Power commissions Paradeep first unit

Published on: 

Essar Power on Monday commissioned the first unit of 30 MW of power at its 120-MW captive Paradeep power plant. In the coming months, the balance units of 90 MW (3 X 30 MW) would be commissioned in phases.

The power plant will meet the power requirement of the company’s 12-million-tonne-per-annum integrated palletisation facility in the State, comprising of a palletisation plant at Paradeep and a beneficiation plant at Dabuna, connected through a 253-km slurry pipeline. Upon completion, Essar Steel would have access to cheap and reliable power supply, thereby improving its competitive edge.

A 220-KV transmission line from the plant switchyard to the main receiving sub-station of the steel plant has already been commissioned for power evacuation. Related infrastructure like port facility for coal handling has already been set up by Essar Ports.

Daily Pioneer
dailypioneer.com