State Water Resources department will spend Rs 196.13 crore on 23 ongoing projects in 12 districts of MP. A maximum of Rs 107.51 crore will be spent on Bhanpura canal project of Gandhi Sagar Dam in Mandsaur district.
Whereas a Rs 38.56 crore will be spent on three works of Barna project and remaining construction works stop dam-cum-barrage at village Dobi in Raisen district, a Rs 12.59 crore on two tunnels between RD 3120 meters to 3570 meters and from RD 5320 to 5635 and works of upstream and downstream complete transition of Bilgaon medium irrigation project in Dindori district, Rs 10.32 crore on construction of reservoirs and canals at Dhanura, Banasi and Jhalmal in Shahdol district, Rs 8.33 crore on five works of Barnu and Madai reservoirs in Jabalpur district, Rs 4.36 crore on spill channel, approach channel, head sluice, flush ware, shoot-fall, earthwork of Taradand reservoir in Anuppur district, Rs 3.36 crore on cement-concrete lining in upstream and downstream’s special improved structure of canal structure of channel from number 0 to 965 up to number 103 and Rs 3 and 2 cement-concrete works on channel 2 of Kulpa-Karanja distributary canal in Balaghat district, Rs 3.64 crore on construction of Bais-Betwa link Project and remaining works of Pipalkhera canal in Vidisha district and Rs 1.33 crore will be spent on remaining works of Katangi reservoir’s dam, sluice, flushware spill channel and structures. Similarly, Rs 88.19 lakh will be spent on construction works of Khajuriya Ghat weir in Sagar district, Rs 79.39 lakh on remaining works of dam and canal of Pahrua reservoir in Katni district and Rs 62.54 lakh will be spent at Pathara, Mohra, Jawa, Chandi, Gaadha Barauli in Rewa district.