Scindia blames CM for delay in water project

Published on: 

Former Union Minister and MP Jyotiraditya Scindia in a letter to Chief Minister Shivraj Singh demanded that immediate advance amount should be paid to the agency Doshiyan Company of Sindh water supply scheme against secured bank guarantee.

According to Scindia, the work of Sindh water supply scheme can be completed within 5-6 months and work of Madhav National Park can be started. It is expected that the permission of Supreme Court can also be received in the month of July.

He accused the State government for the delay. He told chief minister Shivraj Singh Chouhan that Doshiyan Company was demanding Rs 6 crore against secured bank guarantee as advance to complete the remaining work.

In this connection a meeting was held on July 22, 2014 presided over by urban development and environment minister.

The meeting decided that after getting the acceptance of municipal committee, the proposal sent to district planning committee and then to the State government within 10 days for further action. 

The district collector has sent the proposal to the principal secretary of urban administration and development department Bhopal on September 12, 2014 but no advance payment was made to Doshiyan Company to complete the work.

later, in the municipal election in December 2014, the president of Congress was elected and thus, the State government did no permit advance payment so Doshiyan Company. 

Following this, it left the work and wrote letters to municipal committee and state government to clear the account. Scindia said that he talked to Rakshit Doshi, representative of Doshiyan Company which is still ready the work, provided the advance payment is made.