Mayor Alok Sharma inaugurated the girder laying work of the under-construction Cable Stay Bridge at upper lake. He directed the officials to finish the cable stay bridge construction at the earliest. Sharma also directed the fishermen to move their fishing spots immediately.
On this occasion BMC additional Commissioner MP Singh, member of Mayor in Council (MIC) Mahesh Makhvana, Keval Mishra, Dinesh Yadav, Shankar Makoriya, Manjushree Barkiya and City Engineer AK Nanda were present.
To finish the construction works of the Cable Stay Bridge at Kamla Park connecting the old and new city, Mayor Sharma has been monitoring the developments regularly.
Regarding this the Mayor, member of MIC and BMC officials went to visit guarder constructing company Apex Builtsis on April 27, 2016 and directed them to finish the work at the earliest. After that the guarders started reaching Bhopal on May 7. He inaugurated the guarder works on Thursday and made one guarder to be installed right in front of him.
Sharma instructed all the concerned officials and construction company SP Singla Construction representatives to finish the work as soon as possible so that there won’t be any hindrance in the smooth traffic flow.
He also directed the fishermen to remove their spots at the upper lake immediately.
The construction of the Cable Stay Bridge will cost Rs 29.45 crore that will connect the old city to the new city and at the same time add to the beauty of the city.
In this Cable Stay Bridge, 97 guarders of different shapes will be used. All the guarders will reach Bhopal before July 10, 2016.