Lalitpur-Singrauli new rail project is on

Published on: 

The construction work of new railway line projects in Indian Railways is being done at a rapid pace. In this episode, the progress of construction work of Lalitpur-Singrauli total 541 km new rail project is going on very fast.

Under which the work between Lalitpur-Khajuraho (229 km) railway section has been completed and commissioned. It is worth mentioning that the construction work of Rewa-Sidhi (87 km) new rail line project is going on on West Central Railway. Silpara, Govindgarh, Baghwar, Rampur and Churhat railway stations are being built in the middle of Rewa-Sidhi new rail line project.

Sudhir Kumar Gupta, General Manager, West Central Railway, along with Chief Administrative Officer, Construction and Additional Divisional Railway Manager, Jabalpur from the Headquarters, proceeding from Satna-Rewa section on 25 May 2022, proceeded from Rewa station on the bridge of ROB (Road Over Bridge). inspected the work.

After this the General Manager inspected the Satna Railway Station. Keeping in mind the summer season, the water taps and coolers of the station were also tested. Discussions were also held on the proposed second entry gate at Satna station and expansion of parking for two and four wheelers.

Daily Pioneer
dailypioneer.com