Chhattisgarh State Power Generation Company Ltd (CSPGCL) will offer work contract for collection, preparation and analysis of coal samples of its Korba (East) Thermal Power Station.
The sample analysis will be done by NABL Accredited Laboratory , officials informed.
Notably, Chhattisgarh is expected to add 14,140 MW of additional power generation capacity in its thermal plants between November 2015 to March 2022, according to the Central Electricity Authority (CEA) in its perspective transmission plan report prepared for 20 years ( 2014-34).
The objective of the plan is to present broad outlines of the requirement of additional transmission system in the Indian grid during the next two decades.
The National Electricity Plan is under preparation u/S 3(4) of the Electricity Act 2003. This Plan would inter-alia give generation capacity addition for period up to 2021-22 based on integrated resource planning requirements for the country.
In the absence of the generation addition programme for 13th Plan period, an estimate was made considering the ongoing and likely capacity addition for the conventional generation projects.
Major high capacity transmission corridors have already been planned and which are under implementation would be sufficient to meet import/export of power among various regions in the year 2021-22.
This is based on the assumptions of load growth and generation capacity addition .
Initially, the High Capacity Corridors from Chhattisgarh and Odisha were planned with reduced reliability due to uncertainties in generation addition by IPPs. The generations which were associated with these high capacity corridors are coming up in phased manner and till now no major constraint is being faced.
However, with the coming up of more generations, additional transmission strengthening may be required to meet the reliability criteria. This would be taken up with firm status of new generation projects.