The Central Electricity Authority (CEA) has fixed thermal power generation target of 1,619 million units (MU) in May 2017 for the power plants owned by Chhattisgarh State Power Generation Company ltd (CSPGCl), according to the latest CEA data.
The CSPGCl generates power from its DSPM TPS, Korba II, Korba III,Korba West TPS, Marwa TPS.
CEA had fixed monthly power generation target of 1,590 Million Units (MU) for April 2017 for five power stations of CSPGCl.
Notably, the Chhattisgarh Government is targetting 100 per cent household electrification by financial year 2017-18. Notably, as on March 2015, Chhattisgarh had 63.6 households with electrification rate of 84.5 per cent, officials informed.
The State Government is attaching highest priority to power sector and is committed to provide full support to all utilities for ensuring quality power supply, officials informed.
Notably, Chhattisgarh is expected to add 14,140 MW of additional power generation capacity in its thermal plants between November 2015 to March 2022, according to the Central Electricity Authority (CEA) in its perspective transmission plan report prepared for 20 years ( 2014-34).
The objective of the plan is to present broad outlines of the requirement of additional transmission system in the Indian grid during the next two decades.
The National Electricity Plan is under preparation u/S 3(4) of the Electricity Act 2003. This Plan would inter-alia give generation capacity addition for period up to 2021-22 based on integrated resource planning requirements for the country.
In the absence of the generation addition programme for 13th Plan period, an estimate was made considering the ongoing and likely capacity addition for the conventional generation projects. Major high capacity transmission corridors have already been planned and which are under implementation would be sufficient to meet import/export of power among various regions in the year 2021-22. This is based on the assumptions of load growth and generation capacity addition .
Initially, the High Capacity Corridors from Chhattisgarh and Odisha were planned with reduced reliability due to uncertainties in generation addition by IPPs. The generations which were associated with these high capacity corridors are coming up in phased manner and till now no major constraint is being faced.
However, with the coming up of more generations, additional transmission strengthening may be required to meet the reliability criteria. This would be taken up with firm status of new generation projects.The State currently has total renewable energy potential of 4,500 MW which includes solar (grid connected and roof top), wind biomass and small hydro. It has also planned to install solar powered pump sets for agriculture consumers which will benefit 16,000 people.
It may be recalled that there are significantly more number of villages which are to be electrified in Chhattisgarh using the off-grid (solar) mode than the grid-based (conventional power supply.
The State has also launched a ‘Solar Community Irrigation Project’ for drawing water extracted using solar pumps for supplying to the agricultural land of farmers across the State.
The Central government has released Rs 12 lakh each for Raipur and Bilaspur for the Solar City project, officials informed. The total sanctioned funds for the two cities is Rs 43 lakh each.
A total amount of Rs 67.01 crore has been sanctioned for preparation of master plans, solar city cells, promotional activities and installation of renewable energy projects and an amount of Rs 24.16 crore has been released, so far, under Solar City Programme.
Out of seven identified solar cities in Maharashtra, an amount of Rs 7.74 crore has been sanctioned and an amount of Rs 3.04 crore has been released for 6 solar cities.
Notably , Chhattisgarh will procure additional power from renewable energy sources to the tune of approximately 700 MW by FY 2018, officials informed.
With this the average power purchase cost for Chhattisgarh State Power Distribution Company ltd (CSPDCl) based on the above power availability will increase from 2.58 Rs/kWh in FY 2015-16 to 3.12 Rs/kWh in FY 2018, they informed.
The rates have been derived based on cost of power at existing rates and considering no escalation in power purchase cost since it is passing through for the distribution company.
Chhattisgarh has two ‘waste-to-energy’ power plants proposed with a total installed capacity of 10 MW, officials informed. Notably, five Municipal Solid Wastes (MSW) to energy plants with a cumulative installed capacity of 66.5 MW are currently operational/under trial run in the country.
The Chhattisgarh Government has decided to set up a ‘Waste to Energy’ power generation plant in Durg district.
The Government intends to sign a Memorandum of Understanding (MoU) with the Bhilai Steel Plant (BSP) administration for jointly taking up the project, officials informed.
The project is proposed to be undertaken under ‘Swachch Bharat Abhiyan’ under the Government’s solid waste management project.
The proposed ‘Waste to Energy’ plant would utilise waste generated from municipal corporations of Bhilai, Durg, Bhilai-Charoda, two municipal councils mainly Jamul and Kumhari and three Nagar Panchayats mainly Utai, Patan and Gunderdehi.
Notably, the State-owned Chhattisgarh State Power Distribution Company ltd (CSPDCl) in January last year had also announced that it will be purchasing 50 MW of electricity from bio-mass power producers in the State. The company would sign a 20-year agreement with the power producers, officials stated.
Chhattisgarh is among the leading States for implementing bio-mass power projects such as Andhra Pradesh, Maharashtra, Madhya Pradesh, Gujarat and Tamil Nadu, according to Union Ministry of New and Renewable Energy (MNRE). Chhattisgarh had biomass projects generating a total of 249 MW of power as on March 31, 2015.
The total power generation from biomass projects by 12 other States during the aforesaid period in Megawatts is as follows- Andhra Pradesh ( 288), Gujarat ( 30.50), Haryana ( 13.50), Karnataka ( 107.50), Madhya Pradesh (26), Maharshtra ( 198), Odisha ( 20), Punjab ( 68.50), Rajasthan ( 101), Tamil Nadu ( 211.70), Uttar Pradesh ( 54) and West Bengal ( 26).
The Union Ministry of New and Renewable Energy provides Central Financial Assistance at the rate of Rs 25 lakh per Mega Watt in special category States and Rs 20 lakh per Mega Watt for other States with a cap of Rs 1.50 crore per project.
Chhattisgarh produced 527.63 lakh cubic meters of bio-gas from family type bio-gas plants and large bio-gas plants in the entire State during the 11th Five Year Plan period.